Grahm,
I will answer the questions as best I can. If you want more details on anything, you can just ask more questions here.
The build part of the house, from excavation of the foundation until I moved in was 14 months. I took one month off in the middle to go iceboating so I worked on it 13 months. On the weekends I had help from friends and relatives when I was doing things that required multiple bodies. Typically I worked on the house 3-4 hours in the evening and 12-15 hours per day on the weekends. I took 3 weeks of vacation time and worked long days.
I acted as my own GC. I did everything but ICF foundation, cellulose insulation installation, drywall and glass shower enclosure. I had professional help installing the boiler and the gas lines for boiler and stove were run by the Gas company.
So far I have used about 1/3 cord of wood . It is hard to tell exactly how much propane I have used. Not enough to make the gauge move. I have been measuring how much condensate is collected from the boiler (mod con boiler) and doubling it to get a crude idea, based on this I have used less then 20 gallons of propane so far.
In the end I used kohltech windows. There tech people were very helpful, and I got the exact glazing I wanted on the appropriate sides of the house.
The biggest headache for me was getting started. I was starting with raw land so I had to go through the process of surveying, subdividing, perk tests, clearing the land, etc. This part took me about a year to do. The sanitarian was a real PIA and she cost me about 3 months delay for no real reason. This got me started framing in September which I was not happy about. I had hoped to have the whole summer to frame, but it did not happen The other big delay was getting power from the Utility company. This took about 8 months which was crazy. It was partially my fault because I did not know the system. A friend who is a building in a nearby town told me exactly how to expedite the process after I vented to him. Once I did that It only took 7 weeks for them to come out. I worked off a generator, kerosene heater and gas compressor for 8 months. Not fun, but what are you going to do..I was fully enclosed, windows, doors roof and siding around Jan 1.
If I were doing it again, I would tile the entrance to the house, I used bamboo flooring and I am constantly getting snow and mud on it from walking in and the dogs. It is holding up fine but tile would have been better. I originally planned it that way, but changed my mind.
My total costs for the house was about 180 K
Basic breakdown is as follows
Surveying, septic engineering, town permits and fees 12,000$
Costs of obtaining construction to permanent loan and paying points for better terms ~ 5000$ + 8400$ mortgage interest payments during build.
All sitework to include destumping excavation, some fill , installing septic, installing 400 ft of road, trenching for utilities etc was 42000
Drilled Well+pump+ preasure tank =4600$
500 gallon propane tank installed was 2,600$
Cost to bring in electrical power from Utility company 4,600$
All concrete work ie ICF foundation and basement floor + underslab insulation 22,000$
Framing roofing, pine siding exterior trim was 20,000
Ridged insulation 1500
Windows were 8000
Exterior doors 1500
2 panel solar air heater 3200$
Solar hot water heater 4200$
Heating system mod con Boiler + baseboard+ circulators+ indirect tank for DHW= 5000$
Plumbing, rough +finish= 4000
Electrical rough in + finish + Lighting + fans 5000
Cellulose insulation 4000$
Drywall 4100
Tile, cement backerboard materials 2200
Bamboo flooring + underlayment and supplies 4300$
Kitchen cabinets and countertops 1600$
1000$ for stainless chimney and parts.
The rest is paint and trim and random stuff + entry deck. I traded a Hobie 14 for the Woodstove. I owe a batch of people free labor for their projects in the coming years.
In my case it was an expensive lot to develop because it was a long way in the woods. I had to cut off a chunk of land for a house lot so the remaining land could stay in the state forestry program. The whole piece had to be surveyed. The water table in the whole town is fairly high so there was a considerable amount of “Approved” septic fill brought in (in part due to a very conservative sanitarian). On the other hand, approved lots go for about 80- 110K here in the size range I have and I got to that point for about 12K so I was in good shape there. I don’t think you ever get back what you put into extra insulation, solar hot water or solar airheater in terms of resale value so you could not build like this unless you intended to live in it for a good long while.
I hope this helps
Eric